Mandorla
206.2 MW hybrid in Tehama, CA · In queue since April 2023 · Proposed COD April 2028
206.2 MW
Capacity
2
Components
Solar + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5 years
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-01
The Mandorla project is a proposed 206.2 MW hybrid solar and battery energy storage project located in Tehama County, California. The development project consists of a 103.3 MW solar array coupled with a 102.9 MW battery energy storage system. It is interconnected to the PG&E utility via the Glenn 230 kV point of interconnection.
The project is listed in the CAISO interconnection queue as queue ID CAISO-54598, with an entry date of April 17, 2023. The proposed commercial operation date is April 1, 2028. As of the latest data, the interconnection agreement (IA) status is "Not Started".
Generated from interconnection queue and public data sources
State
CA
County
Tehama
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
GLENN 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CAPAY_6_N001
- POI Substation
- Glenn Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Mandorla