Avocado Falls
50.25 MW storage in San Diego, CA · In queue since April 2023 · Proposed COD December 2028
50.25 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
Avocado Falls is a proposed 50.25 MW battery storage project located in San Diego County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54610, with a queue entry date of April 17, 2023. The proposed commercial operation date is December 31, 2028. Interconnection agreement status is listed as "Not Started."
The project, which will interconnect with San Diego Gas & Electric (SDGE) at the AVOCADO 69 kV point of interconnection, consists solely of battery storage with a total capacity of 50.25 MW.
Generated from interconnection queue and public data sources
State
CA
County
San Diego
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
—
Point of Interconnection
AVOCADO 69 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- AVOCADO_6_N001
- POI Substation
- Avocado
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.