Copper Cloud (CAISO-54650) — Project Summary

Queue ID
CAISO-54650
Capacity
200 MW
Technology
Battery
Status
active
Location
Merced, CA
Region
CAISO
Developer
IA Status
Not Started

Copper Cloud

CAISO-54650BetaActiveBatteryCAISOLBNL

200 MW storage in Merced, CA · In queue since April 2023 · Proposed COD December 2031

200 MW

Capacity

1

Components

Battery

3y 1m

In Queue

Not Started

IA Status

COD target: 2031

Interconnection

Total Duration

8y 8m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2031-12-31

About

The Copper Cloud project is a proposed 200 MW battery storage project located in Merced County, California. The project is listed in the CAISO interconnection queue as entry CAISO-54650, with a queue entry date of April 17, 2023. Pacific Gas and Electric (PGAE) is the utility. The proposed commercial operation date is December 31, 2031, and the interconnection agreement (IA) status is "Not Started".

The project is located within the CAISO region and consists solely of battery storage. The point of interconnection (POI) is the Los Banos 500 kV substation. The developer is unknown, and there is no indication of recent news coverage or a link to an existing operating plant.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

Merced

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

PGAE

Entity

CAISO

Service Type

Point of Interconnection

LOS BANOS 500 kV

Data Source

LBNL

CompanyRed Cloud SecuritiesMining.com · 2025-09-10
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_ZP26_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
SNTANLA_6_N001
POI Substation
Los Banos Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (1)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.

ask pi about Copper Cloud