Bonita Bateria 2
123.405 MW storage in Orange, CA · In queue since April 2023 · Proposed COD May 2029
123.405 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
6y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-31
Bonita Bateria 2 is a proposed 123.41 MW battery storage project located in Orange County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54655, with a queue entry date of April 17, 2023. The proposed commercial operation date is May 31, 2029. Interconnection agreement status is listed as "Not Started".
The project, which is being developed within the San Diego Gas & Electric (SDGE) service area, consists of 123.41 MW of battery capacity. The point of interconnection is the Margarita 138 kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Orange
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
—
Point of Interconnection
MARGARITA 138 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MARGARTA_1_N008
- POI Substation
- Margarita Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Bonita Bateria 2