Bonita Bateria
102.91 MW storage in Orange, CA · In queue since April 2023 · Proposed COD May 2029
102.91 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
6y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-31
The Bonita Bateria project is a proposed 102.91 MW battery storage project located in Orange County, California. Interconnection is requested through the CAISO queue, with queue ID CAISO-54656, under utility San Diego Gas & Electric (SDGE). The project entered the queue on April 17, 2023, and is currently listed as active. The proposed commercial operation date is May 31, 2029, and the interconnection agreement status is listed as "Not Started".
The project consists solely of battery storage, with a total capacity of 102.91 MW. The point of interconnection (POI) is the TALEGA 138 kV substation. The developer is not specified in the queue data, and there is no indication of an existing operating plant linked to this project. There is no indication of news coverage related to this project in the provided data.
Generated from interconnection queue and public data sources
State
CA
County
Orange
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
—
Point of Interconnection
TALEGA 138 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- PICO_1_N001
- POI Substation
- Talega Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Bonita Bateria