Tea Leaf Energy Storage
404.3 MW storage in Alameda, CA · In queue since April 2023 · Proposed COD June 2030
404.3 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-01
The Tea Leaf Energy Storage project is a proposed 404.3 MW battery storage project located in Alameda County, California. The project is in the CAISO interconnection queue as entry CAISO-54666, with a queue entry date of April 17, 2023, and a proposed commercial operation date of June 1, 2030. Interconnection agreement status is listed as "Not Started." The project is being proposed within the Pacific Gas & Electric (PGAE) service area.
The Tea Leaf Energy Storage project has been the subject of recent news coverage, with seven articles published in industry and grid publications.
Generated from interconnection queue and public data sources
State
CA
County
Alameda
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
TESLA-TRACY #1
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Tea Leaf Energy Storage