Serenity
305.4 MW generation in Nye, NV · In queue since April 2023 · Proposed COD June 2031
305.4 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-06-01
The Serenity project is a proposed 305.4 MW solar generation facility located in Nye County, Nevada. The project is being developed within the California Independent System Operator (CAISO) region and is interconnected to the Valley Switch 230 kV point of interconnection.
The project, identified as CAISO-54669 in the CAISO interconnection queue, entered the queue on April 17, 2023, with a proposed commercial operation date of June 1, 2031. As of the current data, the interconnection agreement (IA) status is listed as "Not Started." The utility associated with the project is GLW.
Generated from interconnection queue and public data sources
State
NV
County
Nye
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
GLW
Entity
CAISO
Service Type
—
Point of Interconnection
VALLEY SWITCH 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.