Nelson Hills
204.57 MW generation in Nye, NV · In queue since April 2023 · Proposed COD June 2031
204.57 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-06-01
The Nelson Hills project is a proposed 204.57 MW solar generation project located in Nye County, Nevada. The project is being developed within the California Independent System Operator (CAISO) region and is interconnected to the Valley Switch 230 kV point of interconnection. The project entered the CAISO queue as ID CAISO-54671 on April 17, 2023, with a proposed commercial operation date of June 1, 2031. As of the latest data, the interconnection agreement has not yet been started.
The Nelson Hills project has been the subject of recent news coverage, with two articles categorized as regulatory and industry news.
Generated from interconnection queue and public data sources
State
NV
County
Nye
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
GLW
Entity
CAISO
Service Type
—
Point of Interconnection
VALLEY SWITCH 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Nelson Hills