Zeitgeist K Energy Center (CAISO-54682) — Project Summary

Queue ID
CAISO-54682
Capacity
258.47 MW
Technology
Battery
Status
active
Location
San Joaquin, CA
Region
CAISO
Developer
IA Status
Not Started

Zeitgeist K Energy Center

CAISO-54682BetaActiveBatteryCAISOLBNL

258.47 MW storage in San Joaquin, CA · In queue since April 2023 · Proposed COD December 2030

258.47 MW

Capacity

1

Components

Battery

3y 1m

In Queue

Not Started

IA Status

COD target: 2030

Interconnection

Total Duration

7y 8m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-12-26

About

The Zeitgeist K Energy Center is a proposed battery storage project located in San Joaquin County, California, with a total capacity of 258.47 MW. The project is listed in the CAISO interconnection queue as CAISO-54682, with an entry date of April 17, 2023. Pacific Gas and Electric (PGAE) is the utility.

The proposed commercial operation date for the Zeitgeist K Energy Center is December 26, 2030. As of the latest data, the interconnection agreement (IA) status is "Not Started". The point of interconnection (POI) is the KASSON 115 kV substation. The project has appeared in recent news.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

San Joaquin

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

PGAE

Entity

CAISO

Service Type

Point of Interconnection

KASSON 115 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_NP15_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
BANTA_6_N001
POI Substation
Kasson Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Zeitgeist K Energy Center