Ripple Solar
1,878.576 MW hybrid in Kings, CA · In queue since April 2023 · Proposed COD October 2031
1,878.576 MW
Capacity
2
Components
Solar + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-10-03
Ripple Solar is a proposed development project located in Kings County, California, with a total capacity of 1878.58 MW. The project is a hybrid facility consisting of 944.91 MW of solar generation and 933.67 MW of battery energy storage. It is listed in the CAISO interconnection queue as entry CAISO-54684, with a queue entry date of April 17, 2023, and a proposed commercial operation date of October 3, 2031. The interconnection point is at DIABLO-GATES #1, and the project's interconnection agreement status is "Not Started."
The project is in the Pacific Gas & Electric (PGAE) service area. Recent news coverage indicates industry interest in the project.
Generated from interconnection queue and public data sources
State
CA
County
Kings
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
DIABLO-GATES #1
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.