Lupine Energy Center
518.122 MW storage in San Bernardino, CA · In queue since April 2023 · Proposed COD December 2030
518.122 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-26
The Lupine Energy Center is a proposed 518.12 MW battery storage project located in San Bernardino County, California. The project, under development in the CAISO region, consists of a single 518.12 MW battery component.
The project, identified as CAISO-54686 in the CAISO interconnection queue, entered the queue on April 17, 2023, with a proposed commercial operation date of December 26, 2030. Interconnection to the Southern California Edison (SCE) grid is planned at the LUGO 500 kV point of interconnection. As of the latest data, the interconnection agreement (IA) has not yet been started.
Generated from interconnection queue and public data sources
State
CA
County
San Bernardino
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
LUGO 500 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- POI Substation
- Lugo Substation