Coyote Ranch Energy Storage
415.77 MW storage in San Joaquin, CA · In queue since April 2023 · Proposed COD June 2029
415.77 MW
Capacity
2
Components
Battery + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-01
Coyote Ranch Energy Storage is a proposed battery storage project located in San Joaquin County, California, with a total capacity of 415.77 MW. The development project consists of two battery components, one with 2.74 MW and the other with 413.03 MW. It is interconnected to the CAISO grid under queue ID CAISO-54699, with an interconnection queue entry date of April 17, 2023, and a proposed commercial operation date of June 1, 2029. The point of interconnection is LOCKEFORD 230 kV, and the interconnection agreement status is "Not Started."
The project is in the Pacific Gas and Electric (PGAE) service area. Coyote Ranch Energy Storage has been the subject of recent news coverage, with seven articles appearing in categories such as deals, industry, and grid.
Generated from interconnection queue and public data sources
State
CA
County
San Joaquin
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
LOCKEFORD 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LOCKFORD_7_N001
- POI Substation
- Lockeford Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.