311.04 MW storage in San Joaquin, CA · In queue since April 2023 · Proposed COD June 2029
311.04 MW
Capacity
2
Components
Battery + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-01
The Frates project is a proposed 311.04 MW battery storage development in San Joaquin County, California. The project, located within the CAISO region and interconnected with PGAE, consists of two battery components with capacities of 2.74 MW and 308.3 MW.
The project is listed in the CAISO interconnection queue as entry CAISO-54701, with a queue entry date of April 17, 2023, and a proposed commercial operation date of June 1, 2029. As of the latest data, the interconnection agreement (IA) status is "Not Started". The point of interconnection (POI) is the GOLD HILL-EIGHT MILE ROAD substation. The Frates project has been mentioned in recent news coverage related to regulatory matters.
Generated from interconnection queue and public data sources
State
CA
County
San Joaquin
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
GOLD HILL-EIGHT MILE ROAD
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.