Ridge Solar Storage
151.295 MW generation in Inyo, CA · In queue since April 2023 · Proposed COD March 2029
151.295 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
5y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-03-30
Ridge Solar Storage is a proposed solar generation project with a total capacity of 151.29 MW, located in Inyo County, California. The project is in the CAISO interconnection queue as entry CAISO-54710, with a queue entry date of April 17, 2023, and a proposed commercial operation date of March 30, 2029. The interconnection utility is Southern California Edison (SCE), and the interconnection agreement (IA) status is "Not Started".
The Ridge Solar Storage project has been the subject of recent news coverage, with 18 articles related to the project appearing in industry, regulatory, deals, grid, and development news categories.
Generated from interconnection queue and public data sources
State
CA
County
Inyo
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
INYOKERN 115 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- INYOKERN_1_N008
- POI Substation
- Inyokern Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26