Bantam Energy Storage
311.216 MW storage in San Joaquin, CA · In queue since April 2023 · Proposed COD June 2029
311.216 MW
Capacity
2
Components
Battery + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-01
The Bantam Energy Storage project is a proposed 311.22 MW battery storage project located in San Joaquin County, California. The project is in the CAISO interconnection queue as entry CAISO-54715, with a queue entry date of April 17, 2023. The proposed commercial operation date is June 1, 2029.
The project consists of two battery components with capacities of 2.83 MW and 308.39 MW. Interconnection service is being requested from Pacific Gas and Electric (PGAE) at the Eight Mile 230 kV point of interconnection. As of the current data, the interconnection agreement has not yet been started. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
San Joaquin
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
EIGHT MILE 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- EIGHTMI_2_N017
- POI Substation
- Eight Mile Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Bantam Energy Storage