Greenwood Energy Storage 2
513.2 MW storage in San Bernardino, CA · In queue since April 2023 · Proposed COD March 2031
513.2 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
7y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-03-31
Greenwood Energy Storage 2 is a proposed battery storage project located in San Bernardino County, California, within the CAISO region. The development project, with a total capacity of 513.2 MW, is being proposed for interconnection to Southern California Edison (SCE). It entered the CAISO queue as queue ID CAISO-54719 on April 17, 2023, and has a proposed commercial operation date of March 31, 2031. As of the latest data, the project's interconnection agreement (IA) status is "Not Started".
The project consists solely of battery storage, with a total capacity of 513.2 MW. The point of interconnection (POI) is the Rancho Vista 230 kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
San Bernardino
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
RANCHO VISTA 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ETIWANDA_6_N006
- POI Substation
- Rancho Vista Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Greenwood Energy Storage 2