Cabrera Reliability
4.281 MW storage in San Bernardino, CA · In queue since April 2023 · Proposed COD September 2028
4.281 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-15
The Cabrera Reliability project is a proposed 4.28 MW battery storage project located in San Bernardino County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54724, with a queue entry date of April 17, 2023. The proposed commercial operation date is September 15, 2028. Interconnection agreement status is listed as "Not Started."
The project, which will interconnect with Southern California Edison (SCE) at the Lugo 500 kV point of interconnection, consists of 4.28 MW of battery capacity. The project is currently listed as "active" in the CAISO queue. The developer is unknown.
Generated from interconnection queue and public data sources
State
CA
County
San Bernardino
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
LUGO 500 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- POI Substation
- Lugo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Cabrera Reliability