Nelson
103.76 MW generation in Nye, NV · In queue since April 2023 · Proposed COD June 2031
103.76 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-06-01
The Nelson project is a proposed 103.76 MW solar generation project located in Nye County, Nevada. The development project, under the utility GLW, is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54733, with a queue entry date of April 17, 2023. The proposed commercial operation date is June 1, 2031, and the interconnection agreement (IA) status is "Not Started".
The Nelson project has been the subject of recent news coverage, with 20 articles categorized as industry, grid, development, and regulatory.
Generated from interconnection queue and public data sources
State
NV
County
Nye
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
GLW
Entity
CAISO
Service Type
—
Point of Interconnection
VALLEY SWITCH 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14