Solstice A
1,155 MW hybrid in Fresno, CA · In queue since April 2023 · Proposed COD May 2031
1,155 MW
Capacity
2
Components
Solar + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-05-01
Solstice A is a proposed 1155 MW hybrid solar and battery project located in Fresno County, California. The development project, with components of 577.5 MW solar and 577.5 MW battery storage, is in the CAISO interconnection queue as entry CAISO-54739, filed on April 17, 2023. The proposed commercial operation date is May 1, 2031. The interconnection agreement status is listed as "Not Started." The point of interconnection is the MANNING 500 kV substation.
The Solstice A project is being developed within the CAISO region and has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
LSPC
Entity
CAISO
Service Type
—
Point of Interconnection
MANNING 500 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.