Castoria BESS (CAISO-54749) — Project Summary

Queue ID
CAISO-54749
Capacity
61.6 MW
Technology
Battery
Status
active
Location
Santa Clara, CA
Region
CAISO
Developer
IA Status
Not Started

Castoria BESS

CAISO-54749BetaActiveBatteryCAISOLBNL

61.6 MW storage in Santa Clara, CA · In queue since April 2023 · Proposed COD December 2030

61.6 MW

Capacity

1

Components

Battery

3y 1m

In Queue

Not Started

IA Status

COD target: 2030

Interconnection

Total Duration

7y 8m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-12-31

About

The Castoria BESS project is a proposed 61.6 MW battery storage project located in Santa Clara County, California. The project is in the CAISO interconnection queue as entry CAISO-54749, with a queue entry date of April 17, 2023. The proposed commercial operation date is December 31, 2030. Interconnection service will be provided by PG&E at the Metcalf 230 kV point of interconnection. The interconnection agreement (IA) status is "Not Started".

The development project consists solely of battery storage, with a total capacity of 61.6 MW. It is currently listed as "active" in the CAISO queue. The project has appeared in recent news coverage regarding energy storage development in California.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

Santa Clara

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

PGAE

Entity

CAISO

Service Type

Point of Interconnection

METCALF 230 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_ZP26_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
MERIDIAN_6_N101
POI Substation
Metcalf Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.