Charros Energy Center
619.2 MW hybrid in Yuba, CA · In queue since April 2023 · Proposed COD July 2028
619.2 MW
Capacity
2
Components
Solar + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-31
The proposed Charros Energy Center is a 619.2 MW hybrid solar and battery project located in Yuba County, California. The development project consists of a 105 MW solar component and a 514.2 MW battery energy storage system.
The project is listed in the CAISO interconnection queue as entry CAISO-54760, with a queue entry date of April 17, 2023. The proposed commercial operation date is July 31, 2028. As of the latest data, the interconnection agreement (IA) status is "Not Started." The point of interconnection (POI) is the Rio Oso-Colgate & Rio Oso-Round Mountain T-Line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Yuba
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Rio Oso-Colgate & Rio Oso-Round Mountain T-Line
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- VALLEYSC_1_N102
- POI Substation
- Red Mountain
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.