Hiko
360.24 MW storage in Clark, NV · In queue since April 2023 · Proposed COD December 2031
360.24 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-12-02
The Hiko project is a proposed 360.24 MW battery storage development in Clark County, Nevada. The project is located within the California Independent System Operator (CAISO) region and is interconnected to Southern California Edison (SCE) at the Mohave 500 kV point of interconnection.
The project, identified as CAISO-54764 in the CAISO interconnection queue, entered the queue on April 17, 2023. Its proposed commercial operation date is December 2, 2031. As of the latest data, the interconnection agreement (IA) status is "Not Started".
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
MOHAVE 500 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SOPOINT_LNODE-2
- POI Substation
- Mohave Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Hiko