Argos Solar
705.887 MW hybrid in San Bernardino, CA · In queue since April 2023 · Proposed COD June 2030
705.887 MW
Capacity
2
Components
Solar + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-01
Argos Solar is a proposed 705.89 MW hybrid solar and battery energy storage project located in San Bernardino County, California. The development project consists of a 352.25 MW solar component and a 353.64 MW battery energy storage component. It is interconnected to Southern California Edison (SCE) and appears in the CAISO interconnection queue as entry CAISO-54767, with a queue entry date of April 17, 2023.
The proposed commercial operation date for Argos Solar is June 1, 2030. As of the latest data, the interconnection agreement (IA) status is "Not Started". The point of interconnection (POI) is the CALCITE 230 kV substation. The project is currently listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
CA
County
San Bernardino
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
CALCITE 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.