Dove Cove
514.368 MW storage in San Joaquin, CA · In queue since April 2023 · Proposed COD March 2031
514.368 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
7y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-03-14
The Dove Cove project is a proposed 514.37 MW battery storage project located in San Joaquin County, California. Interconnection is requested through Pacific Gas & Electric (PGAE) within the California Independent System Operator (CAISO) queue, under queue ID CAISO-54774. The project entered the CAISO queue on April 17, 2023, with a proposed commercial operation date of March 14, 2031. As of the current data, the interconnection agreement (IA) status is "Not Started".
The project consists entirely of battery storage, with a total capacity of 514.37 MW. The point of interconnection (POI) is the Tesla 500 kV substation. The Dove Cove project is currently listed as "active" within the CAISO interconnection queue.
Generated from interconnection queue and public data sources
State
CA
County
San Joaquin
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
TESLA 500 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- TESLA_1_B1
- POI Substation
- Tesla Substation