Campito Peak
565.77 MW storage in Inyo, CA · In queue since April 2023 · Proposed COD December 2031
565.77 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-12-01
The Campito Peak project is a proposed energy storage development in Inyo County, California, with a total capacity of 565.77 MW. The project, under developer GLW, consists entirely of battery storage. It is currently active in the CAISO interconnection queue as entry CAISO-54777, with a queue entry date of April 17, 2023, and a proposed commercial operation date of December 1, 2031. The interconnection agreement (IA) status is listed as "Not Started." The point of interconnection (POI) is the Trout Canyon 230 kV substation.
Generated from interconnection queue and public data sources
State
CA
County
Inyo
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
GLW
Entity
CAISO
Service Type
—
Point of Interconnection
TROUT CANYON 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CANYONP4_7_GN001
- POI Substation
- Canyon
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Campito Peak