352.643 MW storage in Kern, CA · In queue since April 2023 · Proposed COD December 2029
352.643 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
The Zama project is a proposed 352.64 MW battery storage project located in Kern County, California. It is in the California Independent System Operator (CAISO) interconnection queue as project CAISO-54778. The project, which consists of 352.64 MW of battery capacity, entered the queue on April 17, 2023, with a proposed commercial operation date of December 1, 2029. Interconnection agreement status is listed as "Not Started." The point of interconnection is the WHIRLWIND 230 kV substation.
The Zama project has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
WHIRLWIND 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ASTORIA2_7_N001
- POI Substation
- Whirlwind Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.