Angel Energy Center
615.304 MW storage in Monterey, CA · In queue since April 2023 · Proposed COD December 2030
615.304 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-26
The Angel Energy Center is a proposed 615.3 MW battery storage project located in Monterey County, California. The project, which appeared in recent news coverage, is in the CAISO interconnection queue as entry CAISO-54789, with a queue entry date of April 17, 2023. The proposed commercial operation date is December 26, 2030.
The project's interconnection point of contact is the MOSS LANDING PP 230 kV substation. As of the latest data, the interconnection agreement has not yet been started. The project is being developed within the Pacific Gas and Electric (PGAE) utility service area.
Generated from interconnection queue and public data sources
State
CA
County
Monterey
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
MOSS LANDING PP 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Angel Energy Center