Amberjill Energy
150.68 MW hybrid in Imperial, CA · In queue since April 2023 · Proposed COD July 2029
150.68 MW
Capacity
2
Components
Solar + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-31
Amberjill Energy is a proposed hybrid solar and battery project located in Imperial County, California. The development project has a total capacity of 150.68 MW, consisting of a 100.49 MW solar component and a 50.19 MW battery energy storage system. The project is interconnected to the San Diego Gas & Electric (SDGE) grid at the Imperial Valley 230 kV point of interconnection.
The project, identified as CAISO-54824 in the California Independent System Operator (CAISO) interconnection queue, entered the queue on April 17, 2023. The proposed commercial operation date is July 31, 2029. As of the current data, the interconnection agreement (IA) process has not yet started.
Generated from interconnection queue and public data sources
State
CA
County
Imperial
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
—
Point of Interconnection
IMPERIAL VALLEY 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- WESCAN_7_N002
- POI Substation
- Imperial Valley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.