Patientia Energy
100.43 MW storage in Stanislaus, CA · In queue since April 2023 · Proposed COD July 2029
100.43 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-31
The Patientia Energy project is a proposed 100.43 MW battery storage project located in Stanislaus County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54825, with a queue entry date of April 17, 2023. The proposed commercial operation date is July 31, 2029. Interconnection agreement status is listed as "Not Started."
The project will interconnect to the PG&E grid at the Westley-Los Banos 230 kV Line. The developer is unknown. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Stanislaus
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Westley-Los Banos 230 kV Line
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.