Telluride
205.4 MW hybrid in Fresno, CA · In queue since April 2023 · Proposed COD October 2030
205.4 MW
Capacity
2
Components
Solar + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
7y 6m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-10-30
Telluride is a proposed 205.4 MW hybrid solar and battery project located in Fresno County, California. The development project consists of 102.7 MW of solar capacity coupled with 102.7 MW of battery storage. The project is in the CAISO interconnection queue (queue ID CAISO-54827) with an entry date of April 17, 2023, and a proposed commercial operation date of October 30, 2030. Interconnection service will be provided by PG&E at the ORO LOMA 115 kV point of interconnection. The interconnection agreement has not yet been started.
The Telluride project has been the subject of recent news coverage, with six articles appearing in industry, grid, and deals publications.
Generated from interconnection queue and public data sources
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
ORO LOMA 115 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.