Green Palms
306.6 MW generation in Riverside, CA · In queue since April 2023 · Proposed COD December 2030
306.6 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-31
The Green Palms project is a proposed 306.6 MW solar generation project located in Riverside County, California. The project is in the CAISO interconnection queue as entry CAISO-54832, with a queue entry date of April 17, 2023, and a proposed commercial operation date of December 31, 2030. The point of interconnection is the COLORADO RIVER 230 kV substation, and the project's interconnection agreement status is "Not Started."
The Green Palms project is actively listed in the CAISO queue and has been the subject of 17 recent news articles, primarily covering industry-related topics. The project is proposed to connect to Southern California Edison's (SCE) grid within the CAISO region.
Generated from interconnection queue and public data sources
State
CA
County
Riverside
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
COLORADO RIVER 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CRIMSN_7_CN3
- POI Substation
- Colorado River Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Green Palms