Griffin
205.8 MW storage in Alameda, CA · In queue since April 2023 · Proposed COD March 2028
205.8 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-01
The Griffin project is a proposed 205.8 MW battery storage project located in Alameda County, California. It is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54840, with a queue entry date of April 17, 2023. The proposed commercial operation date is March 1, 2028. As of the latest data, the interconnection agreement (IA) status is "Not Started." The project is interconnected with Pacific Gas and Electric (PGAE) at the point of interconnection (POI) TESLA-TRACY #1.
The Griffin project has been the subject of recent news coverage, with 16 articles appearing in the press. The news coverage primarily focuses on industry trends, with some articles discussing deals and potential hazards.
Generated from interconnection queue and public data sources
State
CA
County
Alameda
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
TESLA-TRACY #1
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26