Zinfandel Storage Center
153.7 MW storage in San Joaquin, CA · In queue since April 2023 · Proposed COD February 2030
153.7 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
6y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-02-15
The Zinfandel Storage Center is a proposed 153.7 MW battery storage project located in San Joaquin County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54841, with a queue entry date of April 17, 2023. Pacific Gas & Electric (PGAE) is the utility. The proposed commercial operation date is February 15, 2030, and the interconnection agreement status is "Not Started".
The development project consists entirely of battery storage, with a total capacity of 153.7 MW. The point of interconnection (POI) is BELLOTA-RIVERBANK. The project is currently listed as "active" in the CAISO queue.
Generated from interconnection queue and public data sources
State
CA
County
San Joaquin
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
BELLOTA-RIVERBANK
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Zinfandel Storage Center