Ulua
105.1 MW storage in Los Angeles, CA · In queue since April 2023 · Proposed COD June 2029
105.1 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-30
The Ulua project is a proposed 105.1 MW battery storage project located in Los Angeles County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54859, with a queue entry date of April 17, 2023. Southern California Edison (SCE) is the utility.
The proposed commercial operation date for the Ulua project is June 30, 2029. As of the latest data, the project's interconnection agreement (IA) status is "Not Started". The point of interconnection (POI) is the Eagle Rock 230 kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
EAGLE ROCK 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- GLNARMC3_7_B1
- POI Substation
- Eagle Rock Switchyard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.