Lince Storage
206.94 MW storage in Fresno, CA · In queue since April 2023 · Proposed COD October 2028
206.94 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-31
The Lince Storage project is a proposed 206.94 MW battery energy storage system located in Fresno County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54875, with a queue entry date of April 17, 2023. The proposed commercial operation date is October 31, 2028. Interconnection service will be provided by Pacific Gas & Electric (PGAE) at the Manning-Los Banos point of interconnection. As of the latest data, the interconnection agreement has not yet been started.
The Lince Storage project has been the subject of recent news coverage related to regulatory matters.
Generated from interconnection queue and public data sources
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Manning-Los Banos
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Lince Storage