Sargadelos Storage
253.72 MW storage in Kern, CA · In queue since April 2023 · Proposed COD October 2028
253.72 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-31
The Sargadelos Storage project is a proposed 253.72 MW battery storage project located in Kern County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54877, with a queue entry date of April 17, 2023. Southern California Edison (SCE) is the utility.
The proposed commercial operation date for the Sargadelos Storage project is October 31, 2028. As of the latest data, the interconnection agreement (IA) has not yet been started. The point of interconnection (POI) is the Whirlwind 500 kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
WHIRLWIND 500 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ASTORIA2_7_N001
- POI Substation
- Whirlwind Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Sargadelos Storage