Horsetail Falls (CAISO-54881) — Project Summary

Queue ID
CAISO-54881
Capacity
102.79978 MW
Technology
Battery
Status
active
Location
Merced, CA
Region
CAISO
Developer
IA Status
Not Started

Horsetail Falls

CAISO-54881BetaActiveBatteryCAISOLBNL

102.8 MW storage in Merced, CA · In queue since April 2023 · Proposed COD January 2028

102.8 MW

Capacity

1

Components

Battery

3y 1m

In Queue

Not Started

IA Status

COD target: 2028

Interconnection

Total Duration

4y 9m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-01-31

About

The Horsetail Falls project is a proposed 102.8 MW battery storage project located in Merced County, California. Interconnection is requested through the CAISO queue, with queue ID CAISO-54881, and Pacific Gas & Electric (PGAE) is the utility. The project entered the queue on April 17, 2023, with a proposed commercial operation date of January 31, 2028. As of the latest data, the interconnection agreement (IA) status is "Not Started".

The proposed project consists solely of battery storage, with a total capacity of 102.8 MW. The point of interconnection (POI) is the Los Banos 230 kV substation. The Horsetail Falls project has appeared in recent news coverage regarding energy storage developments in California.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

Merced

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

PGAE

Entity

CAISO

Service Type

Point of Interconnection

LOS BANOS 230 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_ZP26_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
SNTANLA_6_N001
POI Substation
Los Banos Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Horsetail Falls