Tumey Hills Solar
216.1 MW storage in Fresno, CA · In queue since April 2023 · Proposed COD June 2030
216.1 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-01
The Tumey Hills Solar project is a proposed 216.1 MW battery storage project located in Fresno County, California. The project is in the CAISO interconnection queue as entry CAISO-54885, with a queue entry date of April 17, 2023. The proposed commercial operation date is June 1, 2030. The interconnection agreement status is listed as "Not Started." The point of interconnection is the MANNING 500 kV substation.
The project is being developed within the CAISO region and is interconnected with the LSPC utility. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
LSPC
Entity
CAISO
Service Type
—
Point of Interconnection
MANNING 500 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Tumey Hills Solar