151.85 MW hybrid in Imperial, CA · In queue since April 2023 · Proposed COD July 2029
151.85 MW
Capacity
2
Components
Solar + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-31
Mackerel Energy is a proposed 151.85 MW hybrid solar and battery project located in Imperial County, California. The development project consists of a 101.61 MW solar array coupled with a 50.24 MW battery energy storage system. It is listed in the CAISO interconnection queue under queue ID CAISO-54892.
The project, which is connected to the SDGE utility, entered the CAISO queue on April 17, 2023, with a proposed commercial operation date of July 31, 2029. As of the latest data, the interconnection agreement (IA) status is "Not Started". The point of interconnection (POI) is the IMPERIAL VALLEY 230 kV substation.
Generated from interconnection queue and public data sources
State
CA
County
Imperial
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
—
Point of Interconnection
IMPERIAL VALLEY 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- WESCAN_7_N002
- POI Substation
- Imperial Valley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.