Conduit Energy Storage 2
199 MW storage in San Bernardino, CA · In queue since April 2023 · Proposed COD February 2031
199 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-02-26
Conduit Energy Storage 2 is a proposed 199 MW battery storage project located in San Bernardino County, California. The project is being developed within the CAISO region and is interconnected with Southern California Edison (SCE). It entered the CAISO interconnection queue as queue ID CAISO-54896 on April 17, 2023, with a proposed commercial operation date of February 26, 2031. As of the latest data, the interconnection agreement (IA) status is "Not Started".
The proposed project consists entirely of battery storage, totaling 199 MW of capacity. The point of interconnection (POI) is the Lugo 500 kV substation. Conduit Energy Storage 2 has been mentioned in recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
State
CA
County
San Bernardino
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
LUGO 500 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- POI Substation
- Lugo Substation