Antlia
204.859 MW storage in Monterey, CA · In queue since April 2023 · Proposed COD December 2031
204.859 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-12-01
The Antlia project is a proposed 204.86 MW battery storage project located in Monterey County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54897, with a queue entry date of April 17, 2023. Pacific Gas & Electric (PGAE) is the utility.
The proposed commercial operation date for the Antlia project is December 1, 2031. As of the current data, the interconnection agreement (IA) status is "Not Started". The point of interconnection (POI) is the Moss Landing Power Plant 115 kV substation.
Generated from interconnection queue and public data sources
State
CA
County
Monterey
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
MOSS LANDING PP 115 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Antlia