Collomia Storage
400 MW storage in San Joaquin, CA · In queue since April 2023 · Proposed COD May 2029
400 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
6y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-30
The Collomia Storage project is a proposed 400 MW battery energy storage system located in San Joaquin County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54907, with a queue entry date of April 17, 2023. The proposed commercial operation date is May 30, 2029. Interconnection service will be provided by Pacific Gas & Electric (PGAE) at the BELLOTA-TESLA #2 point of interconnection. The interconnection agreement (IA) status is "Not Started".
The development project consists solely of battery storage, with a total capacity of 400 MW. The project is currently listed as "active" in the CAISO interconnection queue. The developer is unknown.
Generated from interconnection queue and public data sources
State
CA
County
San Joaquin
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
BELLOTA-TESLA #2
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.