Shoals Energy Storage 2
460.86 MW storage in Los Angeles, CA · In queue since April 2023 · Proposed COD June 2029
460.86 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-01
The Shoals Energy Storage 2 project is a proposed 460.86 MW battery storage project located in Los Angeles County, California. The project consists entirely of battery storage. It is listed in the CAISO interconnection queue as queue ID CAISO-54915, with an entry date of April 17, 2023. The proposed commercial operation date is June 1, 2029. Interconnection service will be provided by Southern California Edison (SCE) at the Vincent 500 kV point of interconnection. The interconnection agreement (IA) status is "Not Started".
The development project is located within the CAISO balancing authority area. It is a standalone energy storage project, and has appeared in recent news coverage regarding California's grid-scale battery buildout.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
VINCENT 500 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- VINCENT_2_N101
- POI Substation
- Vincent Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Shoals Energy Storage 2