Amanece Solar
840.447 MW hybrid in Stanislaus, CA · In queue since April 2023 · Proposed COD July 2029
840.447 MW
Capacity
2
Components
Solar + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-31
The Amanece Solar project is a proposed 840.45 MW hybrid solar and battery energy storage project located in Stanislaus County, California. The project consists of a 418.93 MW solar array coupled with a 421.52 MW battery energy storage system. It is interconnected to the PG&E utility network within the CAISO region.
The project, identified as CAISO-54934 in the CAISO interconnection queue, entered the queue on April 17, 2023. Its proposed commercial operation date is July 31, 2029. As of the latest data, the interconnection agreement (IA) has not yet been started. The point of interconnection (POI) is the Westley-Los Banos 230 kV Line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Stanislaus
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Westley-Los Banos 230 kV Line
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.