Grapevine 2 (CAISO-54946) — Project Summary

Queue ID
CAISO-54946
Capacity
505.1 MW
Technology
Battery
Status
active
Location
Clark, NV
Region
CAISO
Developer
IA Status
Not Started

Grapevine 2

CAISO-54946BetaActiveBatteryCAISOLBNL

505.1 MW storage in Clark, NV · In queue since April 2023 · Proposed COD June 2028

505.1 MW

Capacity

1

Components

Battery

3y 1m

In Queue

Not Started

IA Status

COD target: 2028

Interconnection

Total Duration

5y 2m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

About

Grapevine 2 is a proposed 505.1 MW battery storage project located in Clark County, Nevada. The project, under development in the California Independent System Operator (CAISO) region, consists entirely of battery storage. It entered the CAISO interconnection queue as queue ID CAISO-54946 on April 17, 2023, with a proposed commercial operation date of June 1, 2028. The designated point of interconnection is the Eldorado 230 kV substation, and the interconnecting utility is Southern California Edison (SCE). As of the latest data, the interconnection agreement (IA) has not yet been started.

The project is sponsored by an entity within CAISO. Grapevine 2 is an active project in the interconnection queue. Recent news coverage has discussed the development project.

Generated from interconnection queue and public data sources

Project Details

State

NV

County

Clark

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

SCE

Entity

CAISO

Service Type

Point of Interconnection

ELDORADO 230 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_ZP26_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
MCCULLGH_5_N101
POI Substation
Eldorado Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Grapevine 2