Quaking Aspen Storage
307.54 MW hybrid in Kern, CA · In queue since April 2023 · Proposed COD July 2029
307.54 MW
Capacity
2
Components
Solar + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2029
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-31
The Quaking Aspen Storage project is a proposed 307.54 MW hybrid solar and battery energy storage development in Kern County, California. The project consists of a 204 MW solar component and a 103.54 MW battery energy storage component. It is located within the California Independent System Operator (CAISO) region and interconnects to the PG&E utility grid at the GATES-MIDWAY 500kV point of interconnection.
The project, identified by queue ID CAISO-54989, entered the CAISO interconnection queue on April 17, 2023, with a proposed commercial operation date of July 31, 2029. As of the latest data, the interconnection agreement (IA) has not yet been started. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
GATES-MIDWAY 500kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.