Crusade
1,028.2 MW storage in Orange, CA · In queue since April 2023 · Proposed COD December 2028
1,028.2 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
The Crusade project is a proposed 1028.2 MW battery storage development in Orange County, California. The project is located within the CAISO region and interconnects with Southern California Edison (SCE) at the VIEJO 230 kV point of interconnection. It consists of a single 1028.2 MW battery component.
The project, identified as CAISO-55001 in the CAISO interconnection queue, entered the queue on April 17, 2023, with a proposed commercial operation date of December 31, 2028. As of the current data, the interconnection agreement (IA) has not yet been started. The Crusade project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Orange
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
VIEJO 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- VIEJOSC_2_N004
- POI Substation
- Viejo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26