Gibson
154.598 MW storage in Merced, CA · In queue since April 2023 · Proposed COD April 2028
154.598 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5 years
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-14
The Gibson project is a proposed 154.6 MW battery storage project located in Merced County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-55018, with a queue entry date of April 17, 2023, and a proposed commercial operation date of April 14, 2028. Pacific Gas and Electric (PGAE) is the utility. The interconnection agreement (IA) status is listed as "Not Started".
The Gibson project has been the subject of recent news coverage, with 24 articles appearing in industry publications.
Generated from interconnection queue and public data sources
State
CA
County
Merced
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
MERCY SPRINGS SW STA 70 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26