Glossy Garlic Solar
100 MW hybrid in Santa Clara, CA · In queue since April 2023 · Proposed COD March 2027
100 MW
Capacity
2
Components
Solar + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2027
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-01
The proposed Glossy Garlic Solar project is a 100 MW hybrid solar and battery energy storage development in Santa Clara County, California. The project consists of 50 MW of solar photovoltaic generation paired with 50 MW of battery storage. It is located within the California Independent System Operator (CAISO) region and is interconnected to the PGAE utility grid at the LLAGAS 115 kV point of interconnection.
The Glossy Garlic Solar project, identified as CAISO-55035 in the interconnection queue, entered the CAISO queue on April 17, 2023. The developer has proposed a commercial operation date of March 1, 2027. As of the current data, the interconnection agreement (IA) has not yet been started. The project is currently listed as active within the CAISO queue.
Generated from interconnection queue and public data sources
State
CA
County
Santa Clara
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
LLAGAS 115 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Glossy Garlic Solar