HillRich (CAISO-55043) — Project Summary

Queue ID
CAISO-55043
Capacity
309.3 MW
Technology
Battery
Status
active
Location
Santa Clara, CA
Region
CAISO
Developer
IA Status
Not Started

HillRich

CAISO-55043BetaActiveBatteryCAISOLBNL

309.3 MW storage in Santa Clara, CA · In queue since April 2023 · Proposed COD December 2028

309.3 MW

Capacity

1

Components

Battery

3y 1m

In Queue

Not Started

IA Status

COD target: 2028

Interconnection

Total Duration

5y 8m

In Study38%
Queue EntryApr 17, 2023

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

About

The HillRich project is a proposed 309.3 MW battery storage development project located in Santa Clara County, California. The project is interconnected to the CAISO grid at the MILPITAS 115 kV point of interconnection and is in the CAISO interconnection queue as entry CAISO-55043, with a queue entry date of April 17, 2023. The proposed commercial operation date is December 31, 2028.

The project's interconnection agreement status is "Not Started". Pacific Gas and Electric (PGAE) is the utility associated with the project. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

Santa Clara

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

PGAE

Entity

CAISO

Service Type

Point of Interconnection

MILPITAS 115 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_ZP26_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
DIXONLD_1_N002
POI Substation
Milpitas Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.